    REDUCED

    onsite survey POB by 91 days
  • Sixty percent

    REDUCED

    dimensional survey costs by £270,000
  • Clock icon white

    ENABLED COLLABORATION

    between contractors
  • Clock icon white

    408 INSPECTION ISOMETRICS

    generated remotely from the model
  • Clock icon white

    34 RO FABRICATION DRAWINGS

    executed without site surveys
  • Clock icon white

    5 PIPING AND STRUCTUAL

    engineering changes executed without surveys
  • Clock icon white

    168 TIE-IN POINTS CALCULATED

    without a site revisit
  • Clock icon white

    ZERO

    failed to fits

Leading up to a critical 100-day shutdown, our operator client made the decision to significantly increase the workload by moving a large volume of next year's repair campaign into this year.

As Eserv's AS-TEG™ digital twin solution was already in place, the client was able to strategically more than double the workload for the planned shutdown by utilising existing data that was retained within the AS-TEG™ model, without the burden of further visits to site.

Our AS-TEG™ solution enabled 6 different engineering and integrity contractors, used and lead by the operator, to collaborate and execute 34 repair orders and 5 medium-to-large piping and structural engineering modifications.

Within 10 months the AS-TEG™ platform tracked a survey cost-saving of over £270,000, and total manpower days offshore were reduced by 91. The shutdown was complete and delivered to plan, with zero failures-to-fit.

Without Eserv’s AS-TEG™ solution in place, the interruption of COVID-19 would have rendered it impossible to keep to the 100-day shutdown plan and budget.